With the present Phase-VI commissioning, the net cumulative capacity commissioned at Sidhpur site stands at 163.8MW (i.e., 52.5MW + 29.4MW + 25.2MW + 21MW+ 10.5MW + 25.2MW) against the awarded capacity of 250.8MW.