Back
Hot Pursuit
Rajputana Stainless Limited awarded Suzlon Energy a Rs 1.62 crore wind power project and Prozeal Green Energy an Rs 22.71 crore solar project
07-Sep-2026, 06:39
Rajputana Stainless Limited announced on September 7, 2026, that it has awarded a contract to Suzlon Energy Limited for a 2.10 MW wind power project in Gujarat, involving the installation of a Suzlon S120_140_2100kW turbine generator at the Jamjodhpur site, with a project consideration of Rs 1,621 Lacs plus GST. Additionally, the company has awarded a contract to Prozeal Green Energy Limited for an 8 MWp DC solar project in Banaskatha, Gujarat, for Rs 22.71 Crores plus GST, both projects intended to fulfill the company's captive power needs. The wind project is expected to be completed within 11 months, while the solar project’s completion is anticipated within 4 months.